Production runs

Plan a run, start it, record materials and labour, and close it with the actual yield.

Updated 21 Oct 2026

A production run is one batch being made. Go to Manufacturing → Production runs and click New.

1. Plan

Fill in:

  • Product. It's required when finished goods go into stock.
  • BOM: the active recipe to make it with. Its operations are booked onto work centres.
  • Planned quantity: what the recipe should yield. Yield is measured against this.
  • Target batch number, Planned start and Planned end, Facility and Supervisor.

The run is saved as Planned.

2. Start

When production begins, open the run and click Start. The run becomes In progress. If the BOM has operations, start and finish each one as it happens, so the schedule shows where the batch is.

3. Close with the actual yield

When the batch is made, click Complete and enter:

  • the Batch number;
  • the Actual quantity produced;
  • manufacturing and expiry dates.

If yield is below 95% or above 105% of plan, you must write a yield note explaining why before the run can close. An unexplained loss is the first thing an inspector looks for.

Closing creates the batch. It goes into quarantine until QA decides on it, and QA is notified. With Inventory linked, the batch is added to stock in the finished-goods warehouse.

4. Record materials and labour

After closing, record the materials actually used: tick each one and enter the quantity and lot. This builds the batch's genealogy, and with Inventory linked, takes the materials out of stock.

Book labour hours by employee. With Payroll linked, hours are costed at each employee's CTC. An employee without a CTC can't be booked.

Cancel

A run can be cancelled while it's planned or in progress. A completed run can't be cancelled, because it has produced a batch. Hours can't be booked to a cancelled run.

Schedule and work centres

Work centres lists your machines and lines with their working calendar. Production schedule shows every run's operations booked onto them. Click Rebuild after changing priorities, and runs are re-booked around what's already in progress.